Structured Cabling Supply and Installation at Secret Paradise, Palawan — First Progress Update. Introduction The Intercom System Installation Project officially began its first major phase with the start of piping implementation on …
CCTV & Structured Cabling Supply and Installation at Punched Coffee, Johndorf Tower -- 4th progress Update.

Introduction.
The fourth progress update for the CCTV and structured cabling supply and installation at Punched Coffee, located in Johndorf Tower, marks a significant step toward the project’s completion. To accommodate the client’s needs and avoid disrupting the ongoing construction work, our team adjusted their schedule and began working night shifts. This approach ensures a smooth workflow while maintaining efficiency and quality standards.
Night Shift Operations for Client Convenience.
At the request of Punched Coffee, the team transitioned to night-time operations to prevent any interference with the daytime construction activities. Working at night required careful planning and coordination, as lighting, safety measures, and workflow adjustments were put in place to maintain productivity. Despite the change in schedule, the team remained focused and committed to delivering high-quality results while ensuring the construction team’s daytime tasks were undisturbed.
Structured Cabling Progress.
The team continued pulling Cat6 cables through the pre-installed PVC pipes, ensuring each run was properly managed and organized for future network performance. This process included double-checking the cable pathways, securing the cables to prevent slack issues, and verifying that the bends within the PVC conduits met proper standards to avoid damage or signal loss.
This stage is critical in structured cabling projects, as proper installation ensures reliable network connections for CCTV cameras, access points, and other devices. By maintaining a meticulous approach during cable pulling, the team ensures the final network infrastructure will be robust and ready for long-term use.
Nearing Project Completion.
With most of the cabling work completed, the project is now nearing its final stages. The remaining tasks include securing the last cable runs, preparing for terminations, and organizing the cables at the designated connection points. Once completed, the team will begin testing and final verification to ensure optimal performance of the CCTV system and structured cabling network.
Conclusion.
The fourth progress update reflects steady and efficient progress in the CCTV and structured cabling installation at Punched Coffee, Johndorf Tower. By adapting to a night shift schedule, the team successfully balanced the client’s request with project timelines, minimizing disruptions while maintaining quality standards. With completion on the horizon, the project continues to demonstrate our commitment to delivering reliable and well-executed solutions tailored to client needs.
Case Studies
Starlink and Access Point Site Inspection at Tubod Flowing Water Resort. Introduction. In an increasingly connected world, internet connectivity plays a vital role in both business operations and guest experience. Recognizing the …
CCTV Site Inspection at Ai-CHA Warehouse. Introduction. In today’s business environment, security is a top priority—especially for facilities that store valuable goods and equipment. To enhance the safety and monitoring capabilities of …





