Structured Cabling Supply and Installation at Secret Paradise, Palawan -- First Progress Update.
Introduction
The Intercom System Installation Project officially began its first major phase with the start of piping implementation on October 31, 2025. This stage of the project marked a crucial step in establishing the foundational infrastructure for the intercom system across multiple rooms in the facility. Despite facing several on-site challenges and logistical delays, the InstallersPH IT Solutions team diligently carried out the work, ensuring that proper conduit pathways were installed for efficient and secure wiring integration later on.
This report details the team’s progress, the scope of work completed, the challenges encountered during on-site operations, and the overall timeline of the first phase of the project.
Start of the Piping Work.
The project’s initial task focused on setting up the intercom piping system in each designated room. The team began operations on October 31, 2025, working systematically to route conduits that would later house the communication lines necessary for the intercom system. The design plan required precise measurement and alignment of pipes along the walls and ceilings to ensure a clean, efficient layout that adhered to both the technical design and the ongoing construction environment.
Each room’s conduit line was carefully installed to accommodate the intercom’s wiring network. By the end of the first phase, the team successfully completed piping work for a total of 11 rooms. Every pipe was properly secured and aligned according to the system layout to prepare for the next stage of cable pulling and connection.
Dedication and Team Effort.
Completing the first phase of piping required not just technical expertise but also immense dedication from the entire team. The work extended beyond regular hours, with team members spending long days and frequent overtime shifts to meet the project’s schedule and deliver the first phase on time.
The nature of the installation demanded a high level of precision, as the conduit layout would later determine the effectiveness and neatness of the overall intercom system. The InstallersPH team remained committed to maintaining their standard of quality, ensuring each room’s piping followed the project’s design plan while remaining adaptable to on-site conditions.
The completion of 11 rooms within a limited timeframe stands as a testament to the team’s perseverance, efficiency, and collaboration under demanding circumstances.
On-site Challenges.
Despite the visible progress, the team encountered several on-site challenges that slowed down operations. One of the main issues involved the client’s assigned workers who were supposed to assist in coordinating with the installation crew. These workers would occasionally leave their assigned posts, making it difficult for the team to locate them when additional support or coordination was needed.
Furthermore, since the installation crew was not yet fully familiar with the client’s on-site personnel, it became challenging to identify and communicate with the appropriate workers. The lack of proper coordination sometimes led to delays in material transport, workspace preparation, and access clearance, which in turn affected the overall workflow.
The absence of consistent assistance from the client’s side created periods of downtime, forcing the team to adjust their schedules and reallocate manpower to maintain productivity. These setbacks, while frustrating, were handled with patience and professionalism by the team, who continued to push forward despite the unpredictable work conditions.
Construction-Related Delays.
Another major factor affecting the team’s progress was the ongoing construction in the hallway areas. While the piping work inside the rooms was completed, the hallways—where the main intercom trunk lines were to be routed—remained under construction. This made it impossible for the team to proceed with the wiring insertion phase, as doing so could risk damage to the cables and compromise the safety of both the workers and the system components.
Due to the unfinished state of the hallway, the team decided to temporarily halt the wiring installation until the area becomes accessible and secure for work. This decision ensures that the project maintains a high standard of safety and quality, avoiding premature wiring that could lead to future complications.
Even with this temporary limitation, the team ensured that all installed conduits were properly sealed and labeled, making them ready for immediate continuation once the construction of the hallway is completed.
Coordination and Site Management.
Throughout the duration of the first phase, site coordination remained a critical factor. The team communicated regularly with the project supervisors to address the challenges and align on work schedules. Documentation of the day-to-day activities was maintained to track progress, identify causes of delay, and plan adjustments where needed.
Efforts were made to improve collaboration with the client’s assigned personnel by requesting clearer identification and work delegation. This step is expected to enhance communication for the next phases of the project, minimizing idle time and improving workflow efficiency.
Additionally, the team remained proactive in monitoring the overall construction progress, ensuring that once the hallway is cleared and ready, wiring operations can immediately commence without further delays.
Team Perseverance and Work Ethic.
Despite facing coordination problems and construction-related obstacles, the InstallersPH IT Solutions team demonstrated a high level of perseverance and adaptability. Their dedication to completing the first phase within the given timeframe, while ensuring that each pipe installation met quality standards, speaks to the professionalism and reliability that define the team.
The willingness to work overtime and adjust to unpredictable site conditions highlights the team’s strong commitment to delivering excellence in every aspect of their work. Such efforts reflect the company’s broader mission of providing efficient, high-quality IT and communication infrastructure solutions to every client.
Quality assurance was also integrated into each step of the process. The conduits installed were inspected for alignment, support spacing, and connection tightness. Any adjustments required were made immediately to prevent issues during the subsequent wiring stage.
Conclusion and Next Steps.
The completion of the piping installation for 11 rooms marks a significant milestone in the Intercom System Installation Project. It represents the successful completion of the project’s first phase, laying the groundwork for future wiring and system integration.
Although challenges such as on-site coordination issues and hallway construction delays affected progress, the team managed to accomplish the majority of the planned work with diligence and efficiency. Their determination ensured that the project continues to move forward despite unforeseen circumstances.
As the hallway construction nears completion, the next phase will involve wiring insertion and connection testing across all completed conduit lines. Once the site is cleared and safe for work, the team will immediately proceed with pulling intercom cables through the existing pipes and preparing each room for terminal installation.
The first phase stands as proof of the team’s capability to deliver reliable results even under difficult conditions. InstallersPH IT Solutions continues to uphold its reputation for excellence, teamwork, and commitment to quality—setting the tone for the successful completion of the succeeding phases of the Intercom System Installation Project.
Case Studies
CCTV Site Inspection at Ai-CHA Warehouse. Introduction. In today’s business environment, security is a top priority—especially for facilities that store valuable goods and equipment. To enhance the safety and monitoring capabilities of …
RFID Automatic Boom Barrier Supply and Installation for RMC Hospital at Guagua Pampanga – Final Turnover.
RFID Automatic Boom Barrier Supply and Installation for RMC Hospital at Guagua Pampanga – Final Turnover. Introduction. The successful completion and final turnover of the RFID Automatic Boom Barrier and Ticketing System …