AccessPoint Supply and Installation at Santo Niño Village-1st Progress Update.








Introduction.
InstallersPH IT Solutions conducted the first progress visit for the Access Point Supply and Installation project at Santo Niño Village to address the client’s concern about limited WiFi coverage in their home. This initial activity focused on site assessment and equipment testing to determine the most effective setup before the actual installation. The project aims to provide wider, more stable wireless connectivity that will support the client’s daily internet needs across different areas of the house.
Project Background.
The client, Sir Adriane, reported that their existing Globe WiFi router was only able to provide internet access within a small portion of the residence. Important areas such as the main room and the outside space could not reliably connect to the network. This limitation affected both convenience and productivity, especially for activities that require a consistent internet connection. To resolve this, the team recommended the use of additional network devices, specifically a switch and a dedicated wireless access point, to extend coverage and improve overall performance.
Site Visit and Assessment.
The team started their journey at 9:23 AM and arrived at Santo Niño Village at 9:42 AM. Upon arrival, they discussed the issue in detail with Sir Adriane and conducted a quick inspection of the existing network setup. At around 9:58 AM, the team confirmed that the router’s signal range was insufficient to cover the full layout of the house. Factors such as distance, walls, and router placement contributed to the weak coverage in key areas.
Based on the assessment, the team explained that adding a switch would help distribute the network connection properly, while an access point would serve as an additional source of WiFi signal placed in a strategic location. This combination would allow devices to connect seamlessly in the areas where the signal was previously weak or unavailable.
Equipment Testing and Initial Setup.
At 10:07 AM, the team proceeded with testing the switch and access point provided for the project. The purpose of this activity was to ensure that the equipment was fully functional and compatible with the client’s existing Globe router. Basic configuration and power testing were performed to verify that the devices could be integrated smoothly during the actual installation phase.
It is important to note that during this visit, the devices were not yet permanently installed. The focus was on validating performance, checking connectivity, and planning the most suitable installation points within the home. This careful preparation helps avoid issues later and ensures that the final setup will deliver optimal coverage and stability.
Project Status and Next Steps.
After completing the assessment and equipment testing, the team wrapped up the site activity and departed at 10:57 AM. They arrived back at the office at 11:28 AM. This visit officially marks the first progress update of the project. The information gathered and results of the tests will guide the next phase, where the actual mounting, cabling, and full configuration of the switch and access point will be carried out.
Conclusion.
The first progress update for the Access Point Supply and Installation at Santo Niño Village laid the groundwork for a successful network upgrade. Through proper assessment and initial equipment testing, InstallersPH IT Solutions ensured that the proposed solution is well suited to the client’s needs. Once fully installed in the next visit, the switch and access point are expected to significantly improve WiFi coverage, providing Sir Adriane with reliable and accessible internet connectivity throughout his home.
Case Studies
Access Point Site Inspection at Purok Boongon, Tabuelan, Cebu. Introduction. A site inspection was conducted at Purok Boongon, Tabuelan, Cebu to evaluate the feasibility of extending an existing Starlink internet connection to …
CCTV Site Inspection at Guadalupe, Nichols Park subdivision. Introduction. Ensuring the reliability and performance of surveillance systems is essential in maintaining safety and security within residential communities. On this day, InstallersPH IT …