CCTV Supply and Installation at Pacific Grand Villas — Final Update & Turnover Report. Introduction After four days of focused planning, precise execution, and strong collaboration with the homeowner, InstallersPH IT Solutions …
Structured Cabling at Talisay Residential Property -- 8th progress.

Introduction
Building on the successful cable organization and routing through the vertical cable manager, the team progressed with the remaining tasks to prepare the structured cabling system for testing. This phase focused on temporary bundling, termination verification, and ensuring proper signal integrity before final performance validation.
Work Accomplished:
1. Temporary Cable Bundling with Masking Tape
To maintain organization while awaiting permanent bundling solutions:
Used masking tape to temporarily group cables by floor (Ground, Second, Third)
Applied tape at consistent intervals to prevent cable tangling during routing
Ensured tape was not overtightened to avoid cable jacket deformation
Clearly labeled each bundle with floor identification
2. Cable Slack Management
To maintain proper service loops without excess clutter:
Trimmed unnecessary cable lengths while preserving adequate slack
Coiled remaining slack in uniform loops at designated access points
Temporarily secured coils with masking tape for neatness
3. Termination Point Verification
Conducted thorough checks of all connection points:
Validated labeling accuracy at patch panel and wall outlets
Re-seated any questionable RJ45 terminations
Visually inspected punch-down blocks for proper wire seating
4. Preliminary Continuity Testing
Performed basic connectivity verification:
Used handheld tester to confirm end-to-end continuity
Identified and flagged any open or crossed pairs
Documented results for reference during final testing
5. Pathway Finalization
Prepared cable pathways for permanent installation:
Straightened and aligned all cable runs
Adjusted temporary bundling as needed for proper routing
Verified adequate bend radii throughout vertical manager
Conclusion
The team has made significant progress in preparing the structured cabling system for final commissioning. By implementing temporary masking tape bundling, we’ve successfully:
Maintained organized cable routing across all floors while awaiting permanent securing solutions
Preserved cable integrity through proper tension management and bend radius control
Established a solid foundation for upcoming performance testing and permanent installation
This temporary organization method has proven effective in keeping the project moving forward while ensuring we maintain flexibility for any necessary adjustments before finalizing the installation. The system is now well-positioned for the transition to permanent bundling and comprehensive performance validation.
With the physical layout complete and preliminary testing underway, we’re on track to deliver a high-performance, serviceable network infrastructure that meets all design specifications and industry standards. The next phase will focus on replacing temporary measures with permanent solutions and verifying ultimate system performance.