Fiber Optic Cable Wiring and Termination at Havaianas- SM City Cebu.





Site Video.
Fiber Optic Cable Wiring and Termination at SM City Cebu.
Introduction.
On September 3, 2026, the technical team conducted a fiber optic cable wiring and termination service at SM City Cebu. The activity focused on the proper installation, routing, preparation, and termination of fiber optic cables to establish a clean, organized, and reliable network connection. The work was carried out carefully to ensure that the installed fiber cable would provide stable connectivity and support the site’s network infrastructure.
Site Arrival and Preparation.
The team departed for the site at 8:35 AM and arrived at SM City Cebu at 9:11 AM. Upon arrival, the team prepared the necessary tools, equipment, and materials needed for the installation. The work area was also inspected to identify the appropriate cable pathway and determine the most efficient route for the fiber optic cable.
Proper preparation was performed before starting the installation to ensure that the work could be completed safely, efficiently, and with minimal disruption to the surrounding area.
Fiber Optic Cable Wiring.
The main activity involved the wiring and routing of the fiber optic cable. The cable was carefully positioned along the designated pathway to maintain an organized installation. Proper routing was observed to prevent excessive bending, pulling, or unnecessary stress on the cable, which could affect its performance.
The team ensured that the cable pathway was neat and properly arranged. This approach not only helped protect the fiber optic cable but also made the network infrastructure easier to inspect, maintain, and troubleshoot in the future.
Cable Preparation and Termination.
After completing the cable routing, the team proceeded with the preparation and termination of the fiber optic cable. The cable ends were carefully prepared to ensure that the fiber strands were properly positioned for termination.
The termination process required precision and proper handling of the fiber strands. The team maintained cleanliness and carefully aligned the fiber during the procedure to minimize the possibility of connection issues or signal loss. Proper termination is essential in establishing a stable connection between the fiber optic cable and the corresponding network equipment or termination point.
Inspection and Quality Checking.
After the termination work was completed, the installed fiber optic cable was inspected to ensure that the routing and termination were properly completed. The team checked the overall cable arrangement and ensured that the connection points were secure.
The work area was also reviewed to ensure that the installation remained clean and organized. Any excess materials and debris from the work were properly managed to leave the area in good condition.
Completion of Service.
The assigned fiber optic cable wiring and termination works were successfully completed at the site. After finishing the activity, the team departed from SM City Cebu at 12:37 AM and arrived back at the office at 1:06 AM.
The completed installation provided a properly routed and terminated fiber optic connection while maintaining a clean and organized network setup.
Conclusion.
Overall, the fiber optic cable wiring and termination activity at SM City Cebu was successfully completed. The team carefully performed the necessary routing, preparation, and termination procedures to ensure a reliable and properly organized network connection. Through proper installation practices and careful handling of the fiber optic cable, the activity contributed to maintaining a dependable network infrastructure at the site.